DSL are currently working on phase II of a project for one of our clients reassembling The Ram Rig Structure on one of their vessels whilst located in Las Palmas to enable them to commence drilling operations.

July 2020
Ram Rig Structure Splitting and Ressembling

DSL are currently working on phase II of a project for one of our clients reassembling The Ram Rig Structure on one of their vessels whilst located in Las Palmas to enable them to commence drilling operations.

Phase I of the project was to dismantle the structure to allow travel through the Bosphorus passage into the Mediterranean sea.

Work scopes undertaken by our team of Multi-disciplined Rig-Builders in a safe and efficient manner during phase I & phase II of the project included but not limited to the below;

  • Removal/installation of all the interface material at the split point of the ram rig structure, access ladders, utility lines, winch wires and electric cables/tray.
  • Removal/Installation of the riser fingers to allow the space to erect the lifting towers used to lower/raise the top section of the Ram Rig
  • Installing a steel support frame to lower/raise the top section of the ram rig. The frame is designed to allow the jacking and skidding of the top section onto the Fagioli lifting elevator/towers. The steel frame also maintains the geometry of the original structure to minimise alignment issues during transit and re-connection

Galería del proyecto

Ram Rig Structure Splitting and Ressembling — image 1
Ram Rig Structure Splitting and Ressembling — image 2
Ram Rig Structure Splitting and Ressembling — image 3
Ram Rig Structure Splitting and Ressembling — image 4
Ram Rig Structure Splitting and Ressembling — image 5
Ram Rig Structure Splitting and Ressembling — image 6
Compartir: