Conoco Viking Vulcan Decommissioning
Derrick Services UK Limited were awarded a work package to support Royal Boskalis with Decommissioning Support Services including all above water leg cutting throughout the 2019 multi-phase Southern North Sea Decommissioning Campaign.

Derrick Services UK Limited were awarded a work package to support Royal Boskalis with Decommissioning Support Services including all above water leg cutting throughout the 2019 multi-phase Southern North Sea Decommissioning Campaign.
7 Jackets & 4 Topsides were successfully removed from the field and transported ashore for dismantling.
Robust planning, comprehensive pre-works & the adoption of a one team philosophy were a significant element that contributed to the successful project execution.
DSL personnel executed over 38,000 Man-hours on the project (Rope Access & Non Rope Access) without a LTI, this is a credit to all involved in the project including offshore personnel, & the robust onshore support structure.
- Installation of Spider Deck Access
- Cutting & Removal of Caissons and Risers
- Cutting Penetrations for Rigging
- Installation of Fairlead Bollards
- Sling Path Clearance
- Topsides Lift point (Trunnion) Installation
- Topside Separation Cuts at El +17.3
- External Pile Cutting
- Cutting and Removal of Leg extensions at El+7.9
- Installation of Rigging and Steering Wires
- Rigging & Cutting platform Installation
- Sea Fastening of Topsides and Jackets
Project Description
The work scope involved numerous work tasks in what were challenging conditions spanning;
- Onshore Project Management
- Engineering & Fabrication
- Redundant equipment removal
- Installation of lifting points
- Caisson, Riser & J tube Removal
- Sling path Clearing & Air Gapping
- Leg Cutting Platform Installation
- Leg Cutting (Oxy Acetylene)
- Offshore Construction Services
- Rope Access Personnel (Welders, Platers, Pipe-fitters, Riggers, E&I)
Services Provided
- Project Planning
- Engineering and Fabrication
- Rope access Personnel and Equipment
- Offshore Construction Services
- Redundant Equipment Removal
- Communication Tower Removal
Benefits to the client
- Multi-disciplined personnel on the asset creating efficiencies
- Collaborative approach between Client, Construction Contractor and HLV contractor
- Open discussions leading to innovative ideas resulting in cost and time efficiencies
- Open sharing of Information between all parties