Perfuração offshoreNoble Drilling
Noble Valiant Crown, Turndown Sheave and Crane Ram Change-Out
DSL supplied an IRATA rope access rig-building team to Noble Drilling's drillship Valiant to remove and reinstall the crown assembly and 16 turndown sheaves and change out the NOV knuckle boom crane rams.
Métricas principais
- Turndown sheaves removed and refitted
- 16
- Work scopes delivered
- 3
Acesso por CordaEquipes de Construção de SondasRecondicionamento de Equipamentos
Noble Drilling needed an IRATA rope access rig-building team to carry out three separate work scopes onboard the drillship Valiant: removal of the crown assembly, removal and reinstallation of 16 turndown sheaves, and a change-out of the NOV knuckle boom crane rams.
All of the work had to be completed within a specific time slot to meet the client's drilling programme, and much of it involved complex rigging operations in very congested areas of the asset.